Promenade Peak Condo to Replace Substandard Concrete Transfer Slab, Developer Still Targeting Q1 2030 Completion

Promenade Peak Condo to Replace Substandard Concrete Transfer Slab, Developer Still Targeting Q1 2030 Completion

The Straits Times | Perspective | 28 August 2026

A concrete transfer slab in Promenade Peak, a 63-storey condominium in River Valley that is under construction, has failed to meet quality standards and is being dismantled and replaced. Developer Allgreen Properties said the decision to replace the slab entirely was the most prudent approach to safeguard the quality and integrity of the development. Main contractor Woh Hup is bearing the costs, and no cost will be passed to home owners.

63
Storeys
596
Units, 70% Sold
Q1 2030
Target Completion
Woh Hup
Bearing Costs

What a Transfer Slab Does and What Went Wrong

Concrete transfer slabs redistribute and transfer the load from the upper floors of a building to columns or walls below. They are used when the location of columns or walls on the upper floors differs from that of the lower floors, such as when residential units are stacked above a podium or carpark.

In a project construction update to buyers in May, which was seen by The Straits Times, Allgreen Properties managing director Tho Leong Chye said that “during regular and procedural internal quality assessments conducted jointly by us and the main contractor, Woh Hup, it was identified that the supporting concrete transfer slab did not meet stringent quality standards we have established for the project”.

“After carefully considering the rectification options, we have decided that the best course of action is to replace the concrete transfer slab entirely. We believe this is the most prudent and responsible approach to safeguard and uphold the quality and integrity of the development,” Tho said.

A spokesperson for Promenade Peak added in response to queries: “During our regular quality assurance and quality control processes following the completion of concreting works, concerns relating to the quality of the concrete transfer slab were identified.” The spokesperson did not elaborate on what caused the slab to not meet quality standards.

Timeline and Who Pays

Asked if there will be delays in completion, the spokesperson said that “the duration of the demolition works has been assessed and factored into the revised construction timeline”. The spokesperson added: “We are still working towards achieving our estimated Q1 2030 completion, and will in any event endeavour to complete the development in Q2 2030.”

Tho said preparation to dismantle and reinstall the slab started around end-May. The Promenade Peak spokesperson said on 27 August that these works will continue for a few months.

The spokesperson said Woh Hup is bearing the costs of dismantling and reinstating the concrete transfer slab, and that no cost will be passed to home owners.

AsianPrime Perspective: Two points give buyers reasonable comfort here. The issue was caught by the project team’s own quality control after concreting works, then escalated to BCA rather than surfacing through a complaint or incident, and the contractor is absorbing the rectification cost. The completion window has shifted from a firm Q1 2030 to a Q1 with Q2 2030 fallback, which is worth noting if your financing or sale timeline is tied to handover. If you hold a unit here and want to understand your position under the sale and purchase agreement, we are happy to talk it through.

BCA Response and Regulatory Framework

Issues involving concrete transfer slabs are uncommon, the Building and Construction Authority said in response to queries. In Promenade Peak’s case, the project parties identified concerns with the quality of the slab during regular inspections after the completion of concreting works. They carried out further engineering assessments and tests to assess the condition of the slab and alerted BCA.

BCA said the project parties sought approval from the Commissioner of Building Control to carry out the rectification works, and the agency is following up closely with the project team to ensure the project is completed safely.

Singapore has a robust regulatory framework to ensure that its buildings are structurally safe, BCA said. At the construction stage, the builder carries out structural works under the supervision of a Qualified Person and a team of site supervisors. Construction tests by accredited laboratories and post-construction inspections verify that the structural works are carried out in compliance with the approved plans. The agency added that the project parties for Promenade Peak have carried out their responsibilities diligently in identifying and addressing the issue while ensuring structural safety.

Jason Tan, managing principal of Tresca Consult, noted that if the concrete transfer slab is “not constructed in accordance with the approved drawings, or if the materials such as concrete and reinforcement bars do not meet the design strength and workmanship, then rectification work has to be done in order to ensure the integrity of the structures”. He added: “Demolishing and reconstructing the concrete transfer slab will be time-consuming, depending on the volume of concrete to be hacked and the method of hacking.” Tan was commenting in his capacity as an independent observer.

About Promenade Peak

Promenade Peak has 596 units and is 70 per cent sold. It will be the world’s tallest prefabricated prefinished volumetric construction residential building, and will feature the highest infinity pool in Singapore.

The prefabricated prefinished volumetric construction method involves precasting three-dimensional modules such as a bathroom and installing fittings at an off-site facility. These modules are then delivered to the site, hoisted and stacked on top of one another, and installed.

According to the spokesperson, transacted prices for the one-bedroom to five-bedroom units range from S$1.4 million to S$6.6 million. The unit mix includes 80 one-bedroom units, 320 two-bedroom units, 118 three-bedroom units, 57 four-bedroom units and 19 five-bedroom units. There are also two 4,144 sq ft penthouses on the 63rd floor.

Frequently Asked Questions

What is a concrete transfer slab and why does it matter?

Transfer slabs redistribute and transfer the load from a building’s upper floors to columns or walls below. They are used when the location of columns or walls on the upper floors differs from the lower floors, such as when residential units are stacked above a podium or carpark. Because they carry structural load, their integrity is critical.

Will Promenade Peak be delayed?

The developer says the duration of demolition works has been assessed and factored into the revised construction timeline. It is still working towards its estimated Q1 2030 completion and will in any event endeavour to complete the development in Q2 2030. Dismantling and reinstallation began around end-May and will continue for a few months.

Who is paying for the rectification?

Main contractor Woh Hup is bearing the costs of dismantling and reinstating the concrete transfer slab. The Promenade Peak spokesperson said no cost will be passed to home owners.

How was the problem detected?

The project parties identified concerns with the quality of the slab during regular quality assurance inspections after the completion of concreting works. They carried out further engineering assessments and tests, alerted BCA, and sought approval from the Commissioner of Building Control to carry out rectification works.

Sherry Tang, AsianPrime Properties

Own a unit at Promenade Peak?

The completion window has shifted from a firm Q1 2030 to Q1 with a Q2 fallback. If your financing or onward sale is tied to handover, it is worth understanding your position under the sale and purchase agreement.